3.19.4  Checklist – Initial start-up 
After thorough servicing or when the pump is to be put into service for the first time  
(initial start-up) the following checklist must be observed:
 
Supply and discharge line
c
  Suction and discharge pipes are cleaned.
c
  Suction and discharge pipes are checked for leaks.
c
  Suction pipe is protected properly to prevent the ingress of foreign bodies.
 
Characteristics
The characteristics of the pump unit and safety relief valve to be checked  
(pumptype – see name plate, RPM, working pressure, effective power, working  
temperature, direction of rotation, NPSHr etc.).
 
Electrical installation
c
  Electrical installation complies with local regulations
c
  Motor voltage corresponds with mains voltage. Check terminal board.
c
  Make sure that the starting torque is sufficiently high (no star/delta starting will be used).
c
  Motor protection is adjusted properly.
c
  Direction of motor rotation corresponds with direction of pump rotation.
c
  Motor rotation (detached from unit) is checked.
 
Safety relief valve
c
  Safety relief valve (on pump or in piping) is installed
c
  Safety relief valve is positioned correctly. Flow direction of safety relief valve  
corresponds with suction and discharge lines.
c
  The set pressure of the safety relief valve is checked (see nameplate).
 
Jackets
c
  Jackets are installed.
c
  Maximum pressure and temperature of the heating/cooling media have been checked.
c
  The appropriate heating media or coolant is installed and connected.
c
  The installation complies with the safety standards.
 
Drive
Alignment of pump, motor, gearbox etc. is checked.
 
Protection
c
  All guards and safety devices (coupling, rotating parts, excessive temperature) are in place  
and operative.
In case of pumps that may reach working temperatures of 60°C or more, ensure sufficient safety 
guards against accidental contact re in place.
c
  Monitoring system is operational.
3.19.5  Start-up
When the pump is to be put into service the following checklist and procedure must be observed:
c
  Pump is filled with liquid.
c
  Pump is sufficiently preheated.
c
  Suction and discharge valves are fully open.
c
  Start the pump for a short while and check the direction of rotation of the motor and that the 
magnetic coupling is not slipping.
c
  Start the pump and check suction of liquid (suction pressure).
c
  RPM of the pump is checked.
c
  Discharge pipe and seal are checked for leaks.
c
  Proper operation of the pump is verified.