3.19.4 Checklist – Initial start-up
After thorough servicing or when the pump is to be put into service for the first time
(initial start-up) the following checklist must be observed:
(initial start-up) the following checklist must be observed:
Supply and discharge line
c
Suction and discharge pipes are cleaned.
c
Suction and discharge pipes are checked for leaks.
c
Suction pipe is protected properly to prevent the ingress of foreign bodies.
Characteristics
c
The characteristics of the pump unit and safety relief valve to be checked
(pumptype – see name plate, RPM, working pressure, effective power, working
temperature, direction of rotation, NPSHr etc.).
temperature, direction of rotation, NPSHr etc.).
Electrical installation
c
Electrical installation complies with local regulations
c
Motor voltage corresponds with mains voltage. Check terminal board.
c
Make sure that the starting torque is sufficiently high (no star/delta starting will be used).
c
Motor protection is adjusted properly.
c
Direction of motor rotation corresponds with direction of pump rotation.
c
Motor rotation (detached from unit) is checked.
Safety relief valve
c
Safety relief valve (on pump or in piping) is installed
c
Safety relief valve is positioned correctly. Flow direction of safety relief valve
corresponds with suction and discharge lines.
c
The set pressure of the safety relief valve is checked (see nameplate).
Jackets
c
Jackets are installed.
c
Maximum pressure and temperature of the heating/cooling media have been checked.
c
The appropriate heating media or coolant is installed and connected.
c
The installation complies with the safety standards.
Drive
c
Alignment of pump, motor, gearbox etc. is checked.
Protection
c
All guards and safety devices (coupling, rotating parts, excessive temperature) are in place
and operative.
c
In case of pumps that may reach working temperatures of 60°C or more, ensure sufficient safety
guards against accidental contact re in place.
guards against accidental contact re in place.
c
Monitoring system is operational.
3.19.5 Start-up
When the pump is to be put into service the following checklist and procedure must be observed:
c
Pump is filled with liquid.
c
Pump is sufficiently preheated.
c
Suction and discharge valves are fully open.
c
Start the pump for a short while and check the direction of rotation of the motor and that the
magnetic coupling is not slipping.
c
Start the pump and check suction of liquid (suction pressure).
c
RPM of the pump is checked.
c
Discharge pipe and seal are checked for leaks.
c
Proper operation of the pump is verified.