REQUIREMENTS FOR MASSACHUSETTS
For all side wall horizontally vented gas fueled equipment installed 
in every dwelling, building or structure used in whole or in part 
for residential purposes, including those owned or operated by the 
Commonwealth and where the side wall exhaust vent termination 
is  less  than  seven  (7)  feet  above  finished  grade  in  the  area  of 
the venting, including but not limited to decks and porches, the 
following requirements shall be satisfied:
1.  INSTALLATION  OF  CARBON MONOXIDE  DETECTORS. 
At the time of installation of the side wall horizontal vented 
gas fueled equipment, the installing plumber or gas fitter shall 
observe that a hard wired carbon monoxide detector with an 
alarm and battery back-up is installed on the floor level where 
the gas equipment is to be installed. In addition, the installing 
plumber  or  gas  fitter  shall  observe  that  a  battery  operated 
or  hard  wired  carbon  monoxide  detector  with  an  alarm  is 
installed on each additional level of the dwelling, building or 
structure served by the side wall horizontal vented gas fueled 
equipment. It shall be the responsibility of the property owner 
to secure the services of qualified licensed professionals for 
the installation of hard wired carbon monoxide detectors
 
a.  In the event that the side wall horizontally vented gas 
fueled equipment is installed in a crawl space or an attic, 
the hard wired carbon monoxide detector with alarm and 
battery  back-up  may  be  installed  on  the  next  adjacent 
floor level.
 
b.  In the event that the requirements of this subdivision can 
not be met at the time of completion of installation, the 
owner shall have a period of thirty (30) days to comply 
with  the  above  requirements;  provided,  however,  that 
during  said  thirty  (30)  day  period,  a  battery  operated 
carbon  monoxide  detector  with  an  alarm  shall  be 
installed.
2.  APPROVED CARBON MONOXIDE DETECTORS. Each 
carbon monoxide detector as required in accordance with the 
above provisions shall comply with NFPA 720 and be ANSI/
UL 2034 listed and IAS certified. 
3.  SIGNAGE. A  metal  or  plastic  identification  plate  shall  be 
permanently  mounted  to  the  exterior  of  the  building  at  a 
minimum height of eight (8) feet above grade directly in line 
with the exhaust vent terminal for the horizontally vented gas 
fueled heating appliance or equipment. The sign shall read, 
in print size no less than one-half (1/2) inch in size, “GAS 
VENT  DIRECTLY  BELOW.  KEEP  CLEAR  OF  ALL 
OBSTRUCTIONS”.
4.  INSPECTION. The  state  or  local  gas  inspector  of  the  side 
wall  horizontally  vented  gas  fueled  equipment  shall  not 
approve the installation unless, upon inspection, the inspector 
observes  carbon  monoxide  detectors  and  signage  installed 
in accordance with the provisions of 248 CMR 5.08(2)(a) 1 
through 4.
 
(b)  EXEMPTIONS:  The  following  equipment  is  exempt 
from 248 CMR 5.08(2)(a)1 through 4: 
 
 
1.  The  equipment  listed  in  Chapter  10  entitled 
“Equipment  Not  Required  To  Be  Vented”  in  the 
most current edition of NFPA 54 as adopted by the 
Board; and 
 
 
2.  Product Approved side wall horizontally vented gas 
fueled  equipment  installed  in  a  room  or  structure 
separate  from  the  dwelling,  building  or  structure 
used in whole or in part for residential purposes. 
 
(d)  MANUFACTURER  REQUIREMENTS  -  GAS 
EQUIPMENT VENTING SYSTEM NOT PROVIDED. 
When  the  manufacturer  of  a  Product  Approved  side 
wall horizontally vented gas fueled equipment does not 
provide the parts for venting the flue gases, but identifies 
“special  venting  systems”,  the  following  requirements 
shall be satisfied by the manufacturer:
 
 
1.  The referenced “special venting system” instructions 
shall be included with the appliance or equipment 
installation instructions; and
 
 
2.  The  “special  venting  systems”  shall  be  Product 
Approved  by  the  Board,  and  the  instructions  for 
that  system  shall  include  a  parts  list  and  detailed 
installation instruction.
 
(e)  A  copy  of  all  installation  instructions  for  all  Product 
Approved  side  wall  horizontally  vented  gas  fueled 
equipment,  all  venting  instructions,  all  parts  lists  for 
venting instructions, and/or all venting design instructions 
shall  remain  with  the  appliance  or  equipment  at  the 
completion of the installation.