6
Hydraulic and gas pipe line system
6.1  Heating system
Install the CH-system in accordance with present legislation.
The pipe work headers are available in 2 dimensions, i.e. DN65 and DN100 and are 
connected to one another by the flange couplings and gaskets, M12 or M16x55 bolts, 
spring washers and nuts. The low velocity header and the complete installation can then 
be connected to it.
Low velocity header
There are 3 low velocity headers available:
0310335  Low velocity header for 1 or 2 XL boilers to max. 200kW (fig. 6.1.a)
  Boiler connections are 4x 1 1/2", installation connections are 2x 2". The low velocity 
header must be suspended in the pipework. Supplied with automatic air vent, drain 
valve and pocket for temperature sensor T10. 
0310272  Low velocity headers DN65 to 452kW (fig. 6.1.b)
0310273  Low velocity headers DN100 to 960kW
  The low velocity headers comes standard with adjustable feet, automatic air vent, 
drain valve, pocket for temperature sensor T10, M12 or M16x55 bolts, spring washers 
and nuts. The low velocity header can be positioned on either the left or right hand 
side of the pipe work headers. 
0310290  Temperature sensor T3/T10 (fig. 6.1.c)
Every system with 1 or more UB-boilers must be provided with a flow temperature
sensor T10 and must be connected on the master boiler (address 01) to terminal 3,
position 5 and 6. The flow sensor must be placed in the pocket of the low velocity
header.
Set of bends
The low velocity header can be positioned at a 90° angle. A set of bends may be used 
for that purpose. 
0310274  Bends set DN65 flow/return (fig. 6.1.d)
0310275  Bends set DN100 flow/return
Blanking flanges
The ends of the pipe work headers have to be fitted with blanking flanges. The blanking 
flanges come standard with a fully configured delivery, including bolts, spring washers 
and gaskets. 
0310276  Blanking flange set DN65 flow/return 2 items (fig. 6.1.e)
0310277  Blanking flange set DN100 flow/return 2 items
Welded-on flanges
Upon request, welded-on flanges are available to connect CH-pipe lines to the secondary 
side of the low velocity header and to connect the gas line. 
0310336  Welded-on flange set DN65 flow/return 2 items + DN50 gas 1 item (fig. 6.1.f)
0310337  Welded-on flange set DN100 flow/return 2 items + DN65 gas 1 item
Figure 6.1.b
Figure 6.1.d
Figure 6.1.e