gas piping
Contact  your  local  gas  service  company  to  ensure  that  adequate 
gas service is available and to review applicable installation codes 
for your area.
Size the main gas line in accordance with Table 8. The figures shown 
are for straight lengths of pipe at 0.5 in. W.C. pressure drop, which is 
considered normal for low pressure systems. note: Fittings such as 
elbows, tees and line regulators will add to the pipe pressure drop. 
Also refer to the latest version of the national Fuel Gas Code.
Schedule  40  Steel  or  Wrought  Iron  Pipe  is  the  preferred  material 
for  the  gas  line  of  this  water  heater.  It  is  imperative  to  follow  the 
sizing  recommendations  in  the  latest  version  of  the  national  Fuel 
Gas Code if Corrugated Stainless Steel Tubing (CSST) is used as 
the gas line for this water heater.
The heater is not intended for operation at higher than 14.0" W.C.- 
natural gas, (1/2 pound per square inch gage) supply gas pressure. 
exposure  to  higher  supply  pressure  may  cause  damage  to  the 
gas  valve  which  could  result  in  fire  or  explosion.  If  overpressure 
has  occurred  such  as  through  improper  testing  of  gas  lines  or 
emergency malfunction of the supply system, the gas valve must be 
checked for safe operation. Make sure that the outside vents on the 
supply regulators and the safety vent valves are protected against 
blockage. These are parts of the gas supply system, not the heater. 
Vent blockage may occur during ice storms.
taBle 8 - gas supply pipe lengths (in feet)
maximum equivalent pipe length - natural gas only
Input rate 
(bTU/Hr)
Schedule 40 Steel or Wrought Iron Pipe
1/2"
3/4"
1"
1 1/4"
1 1/2"
120,000
20
70
200
200
200
154,000
10
40
150
200
200
180,000
-
30
100
200
200
199,000
-
30
90
200
200
250,000
-
20
60
200
200
275,000
-
10
50
200
200
310,000
-
10
40
150
200
366,000
-
-
30
100
200
390,000
-
-
20
100
200
Fitting Type*
equivalent length in feet
45°ell
0.7
1.0
1.2
1.6
1.9
90°ell
1.6
2.1
2.6
3.5
4.0
Tee
3.1
4.1
5.2
6.9
8.0
natural Gas 0.60 Specific Gravity, 0.50" W.C. Pressure Drop
*Screwed Fittings
It is important to guard against gas valve fouling from contaminants 
in the gas ways. Such fouling may cause improper operation, fire or 
explosion.
If copper supply lines are used they must be internally tinned and 
certified for gas service. before attaching the gas line, be sure that 
all gas pipe is clean on the inside.
To trap any dirt or foreign material in the gas supply line, a sediment 
trap must be incorporated in the piping (see Figure 21). The sediment 
trap must be readily accessible and not subject to freezing conditions. 
Install in accordance with recommendations of serving gas suppliers. 
refer to the latest version of the national Fuel Gas Code.
To prevent damage, care must be taken not to apply too much torque 
when attaching gas supply pipe to gas valve inlet.
Apply joint compounds (pipe dope) sparingly and only to the male 
threads of pipe joints. Do not apply compounds to the first two threads. 
Use compounds resistant to the action of liquefied petroleum gases.
gas meter size – natural gases only
be sure the gas meter has sufficient capacity to supply the full rated 
gas input of the water heater as well as the requirements of all other 
gas fired equipment supplied by the meter. If gas meter is too small, ask 
the gas company to install a larger meter having adequate capacity.
supply gas regulator
The minimum gas supply pressure must not be less than 3.5" w.c. 
(0.87 kPa).
Do  not  subject  the  gas  valve  to  inlet  gas  pressures  of  more  than 
14.0” W.C. (3.48 kPa). A supply gas regulator is necessary if higher 
gas pressures are encountered. See Gas Pressure requirements 
and Supply Gas regulator sections on page 12.
1. Supply gas regulators must be rated above the input btu/hr rating 
of the water heater they supply.
2. Supply gas regulators shall have inlet and outlet connections not 
less than the minimum supply gas line size for the water heater 
they supply. See Table 8. on page 23.
gas piping and sediment trap installation
figure 21.
gas line leak testing
Fire and Explosion Hazard
Leak test before placing the water
heater in operation.
Disconnect gas piping and main gas
shutoff valve before leak testing.
Install sediment trap in accordance
with NFPA 54.
Use joint compound or Teflon tape
compatible with propane gas.
Any time work is done on the gas supply system perform a leak test 
to avoid the possibility of fire or explosion.
1. For  test pressures  exceeding  1/2  psi  (3.45  kPa)  disconnect  the 
water heater and its Main Gas Shutoff Valve from the gas supply 
piping system during testing, see Figure 21. The gas supply line 
must be capped when disconnected from the water heater.
2. For test pressures of 1/2 psi (3.45 kpa) or less, the appliance need 
not be disconnected, but must be isolated from the supply gas line 
by closing the Main Gas Shutoff Valve during testing.
3. Coat all supply gas line joints and connections upstream of  the 
water  heater  with  a  non-corrosive  soap  and  water  solution  to 
test for leaks. bubbles indicate a gas leak. Do not use matches, 
candles, flame or other sources of ignition for this purpose.
4. repair any leaks before placing the water heater in operation.
purging
Gas line purging is required with new piping or systems in which air 
has entered.
Purging should be performed per the current edition of nFPA 54 the 
national Fuel Gas Code.