InstallatIon of vent sYsteM, sIdewall
With the route of the venting system and selection of materials completed, 
as discussed in the section of this manual titled PLANNING THE VENT 
SYSTEM, the through the wall vent terminal in place and the first section
of piping, up to first elbow, installed at the blower it is time to complete the
installation of the venting system for the sidewall installation.
GRADE
*MIN. 12” (30 cm)
ABOVE GRADE OR
*MIN. 12” (30 cm)
ABOVE
ANTICIPATED
SNOW LEVEL
INSTALL A SNORKEL AS SHOWN 
HERE ONLY IF NECESSARY TO 
ACHIEVE THE 12” MINIMUM 
CLEARANCE ABOVE 
THE HIGHEST ANTICIPATED 
SNOW LEVEL.
SNORKEL
fIGure 20
It is recommended that the completion of the venting system start 
at the blower assembly and run to the coupling on the inside wall 
of the vent terminal, Figure18.
The vent system piping should be supported every 5 feet (1.5 m) 
of vertical run and every 3 feet (91 cm) of horizontal run. Follow vent
pipe manufacturer’s instructions for proper joining procedures.
If  necessary  to  achieve  the  12”  minimum  clearance  above
the highest anticipated snow level, install a snorkel as shown 
in bottom portion of Figure 20.
note:  With  the  installation  of  a  snorkel  it  is  necessary  to 
use two 90° elbows that shall be considered along with the
additional  vent  pipe  when  calculating  maximum  equivalent 
feet of venting.
InstallatIon of vertIcal vent sYsteM
A proper flashing or “BOOT” should be used to seal the pipe
where it exits the roof. The total vent system should not exceed 
the  equivalent feet of pipe as listed in Table 1.
Provide support for all pipe protruding through the roof. All piping should 
be properly secured. The vent system piping should be supported  
every 5 feet (1.5 m) of vertical run and every 3 feet (91 cm) of
horizontal run. Follow vent pipe manufacturer’s instructions for proper  
joining procedures.
fIGure 21
IMportant
The  vent  system  must  terminate  so  that  proper  clearances 
are maintained as cited in local codes or the current edition 
of the National Fuel Gas Code (ANSI Z223.1) or the Natural
Gas and Propane Installation Code (CAN/CSA-B149.1) and as  
listed below:
1.  Vent Termination must extend a minimum of 12 inches (30 cm)
above roof or 12 inches (30 cm) above the anticipated snow level
to prevent blockage of the vent termination, as shown in Figures 
20 and 21.