Dimplex WB5E 1 Benutzerhandbuch

Seite von 13
 
7
 
OPERATION 
(All models except WB5E)
 
 
After the electrical and water connections have been made, switch the power 
and water supply on. 
 
The power and ready lights will flash once. The power light will then be 
constantly illuminated to indicate mains supply. 
 
Providing the water supply is present, the machine will start to fill. If the machine 
does not fill to its pre-set level within 4 to 5 minutes the red service light will 
flash 6 times. If this happens, check that the water stop valve is turned on. If the 
valve is on, check that the small plastic filter in the water inlet solenoid on the 
machine is not clogged with debris. To clear the service light, switch the 
machine off and then back on again. 
 
When the correct temperature has been reached, the ready light will be 
illuminated, wait at least 10 minutes after the ready light illuminates before 
starting to draw water (on first installation only). Your machine does not fill 
completely at once. The water input is electronically controlled to obtain 
maximum output, temperature and efficiency. 
 
In daily use, switch on and wait for the ready light to illuminate. The water will 
then be at the correct temperature and the boiler ready to use. We recommend 
that you switch the power supply to the boiler off overnight and when the unit is 
not in use.