Part 1
HI-POT TESTER:
A  “Hi-Pot”  tester  is  shown  in  Figure  7.  The  model 
shown  is  only  one  of  many  that  are  commercially 
available. The tester shown is equipped with a voltage 
selector switch that permits the power supply voltage 
to be selected. It also mounts a breakdown lamp that 
will illuminate to indicate an insulation breakdown dur-
ing the test.
Stator inSulation reSiStance teSt 
(12-20 kW)
GENERAL:
Units  with  air-cooled  engine  are  equipped  with  (a) 
dual  stator  AC  power  windings,  and  (b)  excitation  or 
DPE  winding.  Insulation  tests  of  the  stator  consist  of 
(a) testing all windings to ground, (b) testing between 
isolated  windings,  and  (c)  testing  between  parallel 
windings.  Figure  8  is  a  pictorial  representation  of  the 
various stator leads on units with air-cooled engines.
TESTING ALL STATOR WINDINGS TO GROUND:
1.  Disconnect stator output leads 11 and 44 from the gen-
erator main line circuit breaker.
2.  Remove stator output leads 22 and 33 from the neutral 
connection and separate the two leads.
3.  Disconnect Wires  11  and  22  from Voltage  Regulator.  
Ensure these wires are not touching any other compo-
nents on the generator.
2
6
11P
44
33
22S 
(12-20 kW)
22P
11S 
(12-20 kW)
Figure 8. Stator Winding Leads
4.  Connect the terminal ends of Wires 11, 22, 33 and 44 
together. Make sure the wire ends are not touching any 
part of the generator frame or any terminal.
5.  Connect  the  red  test  probe  of  the  Hi-Pot  tester  to  the 
joined terminal ends of stator leads 11, 22, 33 and 44. 
Connect the black tester lead to a clean frame ground 
on  the  stator  can. With  tester  leads  connected  in  this 
manner, proceed as follows:
a.  Turn the Hi-Pot tester switch OFF.
b.  Plug  the  tester  cord  into  a  120  volt  AC  wall 
socket  and  set  its  voltage  selector  switch  to 
“1500 volts”.
c.  Turn  the  tester  switch  ON  and  observe  the 
breakdown  lamp  on  tester.  DO  NOT  APPLY 
VOLTAGE  LONGER  THAN  1  SECOND.  After 
one (1) second, turn the tester switch OFF.
If the breakdown lamp comes on during the one-sec-
ond test, the stator should be cleaned and dried. After 
cleaning and drying, repeat the insulation test. If, after 
cleaning  and  drying,  the  stator  fails  the  second  test, 
the stator assembly should be replaced.
6.  Proceed to the Voltage Regulator. Each winding will be 
individually tested for a short to ground. Refer to Steps 
5a-5c and perform the same test on the following wires:
Wire 
Number
Winding
22S
Sense Lead Power
11S
Sense Lead Power
6
Excitation
2
Excitation
0
Ground
4
Positive to Brush Ground
TEST BETWEEN WINDINGS:
1.  Disconnect  Stator  Output  Leads  11  and  44  from  the 
generator main line circuit breaker.
2.  Remove Stator Output Leads 22 and 33 from the neutral 
connection and separate the two leads.
3.  Disconnect  Wires  11,  22,  2,  and  6  from  Voltage 
Regulator.  Ensure  these  wires  are  not  touching  any 
other components on the generator.
4.  Connect  the  red  tester  probe  to Wire  2.  Connect  the 
black tester probe to Stator Lead 11. Refer to Steps 5a 
through  5c  of “TESTING  ALL  STATOR WINDINGS TO 
GROUND” on previous page.
5.  Repeat Step 4 between Wire 2 and Stator Lead 33.
6.  Repeat Step 4 between Stator Lead 11 and Stator Lead 33.
Stator inSulation reSiStance teSt 
(8-10 kW)
GENERAL:
Units  with  air-cooled  engine  are  equipped  with  (a) 
dual  stator  AC  power  windings,  and  (b)  excitation  or 
DPE  winding.  Insulation  tests  of  the  stator  consist  of 
(a) testing all windings to ground, (b) testing between 
isolated  windings,  and  (c)  testing  between  parallel 
windings.  Figure  8  is  a  pictorial  representation  of  the 
various stator leads on units with air-cooled engines.