2.11.7 ELECTRICAL SYSTEM
Make sure the generator is properly connected to an
approved earth ground and/or ground rod.
Make sure the generator battery is fully charged,
properly installed and interconnected, and ready for
use.
Check to ensure that there are no loose electrical con-
nections. Restrain any loose wires to keep them clear
of any moving generator set components.
3.1
USING AN ENGINEERED “GTS”
TRANSFER SWITCH
When required, the pre-packaged standby generator
can be installed with an engineered Generac “GTS”
type automatic transfer switch.
In this application, the GTS is responsible for utility
sensing, weekly exercising, and load transferring.
Position two of the four-position dip switch is used to
turn over this control to the GTS.
Pos2 ON — GTS Application
• The generator’s control board will NOT monitor
utility.
• The control board will NOT perform a weekly exer-
cise. (The five red LEDs will not flash in this
mode.)
• The control board will NOT activate the transfer
output.
• The control board WILL monitor all engine condi-
tions and shut down on all the faults listed in this
document.
Pos2 OFF — ATS Application
• The generator’s control board will perform all of
the automatic features listed in this document.
• The two-wire start connections should NOT be
used.
GTS Mode Operation
When in GTS mode, the generator’s control board
will respond as follows based on the AUTO/OFF/
MANUAL switch position.
OFF — The generator will not start and run in this
position.
MANUAL — The control board will start and run the
generator whenever the switch is in the manual posi-
tion.
AUTO — The control board will monitor the two-wire
start circuit. When a two-wire start is issued the con-
trol board will immediately start and run the genera-
tor. Whe the two-wire start is removed the control
board will immediately stop the generator.
NOTE:
If the generator is installed in conjunction with an
engineered GTS type transfer switch, refer to the
applicable transfer switch manual for exact oper-
ating parameters and timing sequences.
3.2
CONTROL CONSOLE
COMPONENTS
The components of a home standby generator control
console (Figure 3.1) are as follows:
Figure 3.1 - Home Standby Generator Panel
3.2.1 AUTO/OFF/MANUAL SWITCH
Use this three-position switch as follows:
• Set the switch to AUTO for fully automatic opera-
tion. See “Automatic Operation” (Section 3.5).
• Set switch to MANUAL position to crank and start
the generator engine.
• Set switch to OFF position to shut down an oper-
ating engine. With OFF selected, operation will not
be possible.
With switch set to AUTO, engine can crank and
start suddenly without warning. Such automat-
ic start up normally occurs when utility source
voltage drops below a pre-set level. To prevent
possible injury that might be caused by such
sudden starts, set AUTO/OFF/MANUAL switch
to OFF before working on or around the unit.
Then, place a “DO NOT OPERATE” tag on con-
trol console.
!
DANGER
‹
E
US
U
F
F
E
US
U
F
(SEE OWNER'S MANUAL FOR COMPLETE LED DETAILS)
5 FLASHING RED LED'S = EXERCISER NOT SET
FLASHING GREEN LED = NO UTILITY SENSE
TO SET EXERCISER TIME
1) PLACE AUTO/OFF/MANUAL SWITCH TO AUTO POSITION.
(IN AUTO MODE ONLY) SOLID GREEN LED = SYSTEM READY, UTILITY POWER ON
OFF
EXERCISE
TIME
ON
SET
LED INDICATORS:
RED LED'S = INDIVIDUAL FAULT
MANUAL
OFF
AUTO
0E7194
OVER CRANK
AUTO/OFF/MANUAL
SWITCH
15A FUSE
MAIN
POWER
4A FUSE
BATTERY
CHARGER
SET
EXECISER
TIME
SWITCH
RED LED
GREEN LED
‹
Section 3 - Operation
QUIETSOURCE
Liquid-cooled 30 kW Generators