Omron CPM1A Benutzerhandbuch

Seite von 176
6-3
Section
Handling
135
Operation Procedure
Start
Yes
No
Change the mode of the PC to PRO-
GRAM mode.
Mount the EEPROM to the
CPM1-EMU01-V1.
After 2 or 3 s, check if the indicator is
lit green.
See the note on
the right.
Press the DOWNLOAD TO PLC But-
ton.
Check if the indicator is blinking
green (indicating that downloading
has started).
Yes
No
See the note above.
Check if the indicator is lit green
(indicating that downloading has
been successfully completed).
Yes
No
See the note above.
Remove the Expansion Memory Unit
from the PC.
End
Mount the EEPROM to the
CPM1-EMU01-V1 before downloading.
Confirm the safety of the system.
Note
If the indicator is not lit at all, lit red or
blinks red, downloading will not be
possible. In this case, check the fol-
lowing items.
Is the connector properly con-
nected?
Is the EEPROM properly mounted?
Are the EEPROM specifications cor-
rect?
Are the peripheral port communica-
tions settings correct?
Connect the CPM1-EMU01-V1 to the
PC’s peripheral port.
Confirm the orientation of the connector
before connecting the CPM1-EMU01-V1.
Before actual operation, check the contents
of the ladder program and the DM area, as
well as the expansion instruction settings.
Check the program.