Installation Guide - Overview 
50 
  HC900 Hybrid Controller Installation and User Guide 
Revision 5 
  
9/03 
Table 10 - Site and Equipment Preparation 
Step Procedure 
Reference 
Referring to Site Planning Documentation, ensure that 
sufficient numbers of the following items are on hand: 
• 
Racks (4-, 8- and 12-slot)  
• 
Power Supplies (1 per rack) 
• 
Controller Module or Scanner (1 per rack) 
• 
I/O Modules (correct type for each configured slot) 
• 
Terminal Blocks, Barrier or Euro style, (1 for each I/O 
Module) 
• 
Jumpers 2-position or 10-position, (for designated 
Terminal Blocks) 
• 
Tie Wraps (1 or 2 for each Terminal Block) 
• 
I/O Label (one per terminal block, by module type) 
• 
Filler Block Cover (1 for each slot not occupied by an 
I/O Module)  
• 
Blank label (1 for each Filler Block Cover) 
• 
Grounding Bars for I/O wiring shields (1 or 2 for each 4-
slots in each rack) 
• 
Wiring terminal lugs (for connecting I/O shields to 
grounding bars) 
• 
Sheet metal screws, steel #10 or M4, for mounting racks 
in enclosures (4 screws for 4-slot racks, 8 screws for 8- or 
12-slot racks) 
Site Planning Documentation  
In this Manual: 
•  Section on Pre-Installation 
Planning. 
•  Sections on installation 
•  Appendix A 
 
Install (or verify correct installation of) enclosures for HC900 
Controllers and ancillary equipment: 
• 
Mounting rails or flat-panels 
• 
(for cabinet with multiple HC900 Chassis): 
− 
grounding bus 
− 
barrier strip for AC power 
• 
Master control Relay 
Site Plan Documentation and 
this section of this manual 
 
 
 
 
 
 
Install (or verify correct installation of) enclosures ("closets") 
for networking devices: 
Appendix A.  
Note : Some networking 
devices may share enclosures 
with HC900 Controller 
components.