6
Start-Up
Compare the setting of the nominal output voltage of the UPS 
with  the  rated  voltage  valid  in  your  country.  The  factory 
presetting is 230 V. Changes to 220 VAC or 240 VAC can be 
made with the software “CompuWatch”.
Switching on the PROTECT 1. on the mains
1.
Make  sure  that  all  connections  have  been  made 
according to the installation instructions.
2.
Make sure that all loads are switched off.
3.
Put  the  “maintenance  switch”  manual  bypass 
switch  (no. 3,  p.  26/27)  on  the  back  of  the  UPS 
back  to  the  “USV “  position.  Next  fasten  the  cover 
again with the 4 previously removed screws.
4.
Now insert the back-up fuse in your low-voltage main 
distribution  (where  the  UPS  system  is  connected  to 
the  mains  on  the  input  side)  or  switch  on  the 
corresponding line protection switch there. 
5.
Next  actuate  the  mains  input  miniature  circuit 
breakers  on  the  UPS  (no. 2,  p.  26/27).  Move  this 
to the "ON" position.
i
Factory presetting: The loads are supplied via 
the  integrated  bypass,  which  connects  the 
phase L1 with the UPS output. Do not switch on 
your loads yet, however.
6.
Now switch on the inverter of the UPS. To do this, 
press the ON pushbutton for approx. 2 seconds.
7.
After switching on, the UPS carries out a self-test, 
during which the LED’s for load and battery state
go  on  and  off  consecutively  in  increasing  order. 
After  the  successful  synchronization  of  the 
inverter, the Inverter LED lights up a few seconds 
later,  whereby  the  UPS  is  now  in  normal 
operating mode. When the mains supply is intact 
(mains  within  tolerance),  the  "Line"  LED  also 
lights up.