Cisco Cisco ASR 1000 Series 40Gbps SPA Interface Processor Informationshandbuch

Seite von 3
 
 
Product End-of-Life Notice
 
© 2011 Cisco and/or its affiliates. All rights reserved. This document is Cisco Public Information. 
Page 1 of 3 
End-of-Sale and End-of-Life Announcement for 
the Cisco 1-Port 10 Gigabit Ethernet Shared 
Port Adapter 
EOL7289 
Cisco announces the end-of-sale and end-of life dates for the Cisco 1-Port 10 Gigabit 
Ethernet Shared Port Adapter. The last day to order the affected product(s) is July 19, 
2012. Customers with active service contracts will continue to receive support from 
the Cisco Technical Assistance Center (TAC) as shown in Table 1 of the EoL bulletin. 
Table 1 describes the end-of-life milestones, definitions, and dates for the affected 
product(s). Table 2 lists the product part numbers affected by this announcement. For 
customers with active and paid service and support contracts, support will be 
available until the termination date of the contract, even if this date exceeds the Last 
Date of Support shown in Table 1. 
Table 1. 
End-of-Life Milestones and Dates for the Cisco 1-Port 10 Gigabit Ethernet Shared Port Adapter 
Milestone 
Definition 
Date 
End-of-Life Announcement 
Date 
The date the document that announces the end of sale and end of life of a product is 
distributed to the general public. 
July 20, 2011 
End-of-Sale Date 
The last date to order the product through Cisco point-of-sale mechanisms. The product 
is no longer for sale after this date. 
July 19, 2012 
Last Ship Date: 
HW 
The last-possible ship date that can be requested of Cisco and/or its contract 
manufacturers. Actual ship date is dependent on lead time. 
October 17, 2012 
End of SW Maintenance 
Releases Date: 
HW 
The last date that Cisco Engineering may release any final software maintenance 
releases or bug fixes. After this date, Cisco Engineering will no longer develop, repair, 
maintain, or test the product software. 
July 19, 2013 
End of Routine Failure 
Analysis Date: 
HW 
The last-possible date a routine failure analysis may be performed to determine the cause 
of hardware product failure or defect. 
July 19, 2013 
End of New Service 
Attachment Date: 
HW 
For equipment and software that is not covered by a service-and-support contract, this is 
the last date to order a new service-and-support contract or add the equipment and/or 
software to an existing service-and-support contract. 
July 19, 2013 
End of Service Contract 
Renewal Date: 
HW 
The last date to extend or renew a service contract for the product.  
October 17, 2016 
Last Date of Support: 
HW 
The last date to receive service and support for the product. After this date, all support 
services for the product are unavailable, and the product becomes obsolete. 
July 31, 2017 
 
HW = Hardware 
OS SW = Operating System Software  App. SW = Application Software