Cisco Cisco Packet Data Gateway (PDG) Installationsanleitung

Seite von 195
ASR 5500 Hardware Platform Overview   
▀  Chassis 
 
 
▄  ASR 5500 Installation Guide 
16 
   
Power Filter Units (PFUs) 
Two PFUs mount at the top front of the chassis. Each PFU supports four power planes. 
A total of eight -48 VDC, 80-amp power feeds are required for a full chassis. The eight feeds operate in a 4+4 redundant 
configuration. In lab environments where power redundancy is not required, four 80-amp lines can be used. For 
additional information on power requirements, see the Technical Specifications chapter. 
Cable Management System 
The ASR 5500 cable management system consists of two components. The first is a tray that mounts at the rear of the 
chassis immediately below the card cage. The second is a cable management bracket that mounts to the front panel of 
each Management Input/Output card (MIO/UMIO). 
Network cables are fed from either side or both sides of the tray and are then routed to the MIO/UMIO ports. The cables 
are secured to the cable management brackets on the MIO/UMIOs via cable ties or hook-and-loop straps, and within the 
cable management tray via hook-and-loop straps.