Cisco Cisco Process Orchestrator 3.1 Betriebsanweisung
14-96
Cisco Process Orchestrator 3.1 User Guide
Chapter 14 Using SAP Adapters
SAP RFC Adapter
Note
This method requires the ABAP Add-On.
SM50 – Analyze Long Running Processes Method Properties
Use the SM50 - Analyze Long Running Processes method to determines if any SAP work processes of
a specified type have been executing longer than the specified time.
a specified type have been executing longer than the specified time.
Date (yyyMMddHHmmss)
Status date for the job
Note
To get the results in the last X minutes from the current time,
this field should remain blank and specify the number of
minutes in the Last X minutes prior to specified date field.
this field should remain blank and specify the number of
minutes in the Last X minutes prior to specified date field.
Note
To get the results within a specified date range (To/From),
you must enter the value for the ending date in this field and
specify the amount of minutes in the Last X minutes prior to
specified date field.
you must enter the value for the ending date in this field and
specify the amount of minutes in the Last X minutes prior to
specified date field.
Last X minutes prior to the
specified date
specified date
Time period, in minutes, for selecting jobs based on the date.
After Event (wildcard)
Specify the job scheduling event to scheduled job so that it can only
be released via a SAP Background Processing Event. The job will
not execute until this event has been triggered by the SAP runtime
system. Job scheduling events are configured in SAP Background
Processing configuration, accessed via SAP Transaction SM62.
be released via a SAP Background Processing Event. The job will
not execute until this event has been triggered by the SAP runtime
system. Job scheduling events are configured in SAP Background
Processing configuration, accessed via SAP Transaction SM62.
Duration
For jobs that have completed, the amount of time job took between
start and end. For example, set to 1000 for any jobs that executed for
longer than 100 seconds.
start and end. For example, set to 1000 for any jobs that executed for
longer than 100 seconds.
Delay
For jobs that have started, the minimum amount of time job was on
hold between its scheduled start time and the time that it was able to
start. For example, set to 100 to select any jobs that were delayed by
100 seconds or more.
hold between its scheduled start time and the time that it was able to
start. For example, set to 100 to select any jobs that were delayed by
100 seconds or more.
Field Description