Moxa ZB-PM3-T Benutzerhandbuch
Software Installation
After physically installing the Sub-1G module, the module will be recognized on
the new system board after the following steps.
Steps for Installation
1.
Apply power to the system board.
2.
Run DCU-8620-T application program. Make sure it could communicate with
Sub-1G module(ZB-WAN1-T and ZB-DCU3-T).
3.
Apply power to the Power Meter. Make sure the LED of “Ready” light-on on
Power Meter.
4.
Run DCU-8620-T application program, make sure it could read data from
Power Meter through the air.