Goliath Solutions SPIDER-10-001 Benutzerhandbuch

Seite von 43
              FSM Cable Installation & MEU Activation  
 
Page 17 of 43      Rev. 1A,   Rev. Date: 8/31/2006 
Use or Disclosure of this document is covered under the Non-Disclosure Agreement executed between the 
prospective vendor and Goliath Solutions LLC. 
 
Appendix B – Installation Check List 
 
Task 
Status 
1)  Complete the pre- installation tasks. 
 
2)  Verify that you have all the supplies listed in Appendix A available for the store 
installation. 
 
3)  Checked in with the Store Manager. 
 
4)  Checked in with the Goliath Help Desk. 
 
5)  Verified the location of the Goliath equipment package and its contents. 
 
6)  Performed the MEU Survey and determined the location of the MEU. 
 
7)  Performed the Equipment survey and determined the location of all the 
transmitters and receivers 
 
8)  Verified that test tags were installed during the pre-installation survey and are 
still present in the store or installed the Test Tags for the Store 
 
9)  Input the test tag information in SYSMON. 
 
10) Placed the tags on the displays in the current campaign.   
 
11) Recorded the information on the Goliath tag Installation Report. 
 
12) Configured and activated the MEU. 
 
13) Test the MEU with the Goliath Help Desk. 
 
14) If the system is functioning ok, Check out with Goliath Help Desk 
 
15) Walk through store and verify all the supplies from the installation have been 
cleaned up. 
 
16) Check out with the Store Manager and verify there are no issues with the store 
 
17) Leave the store. 
 
18) When you get home update QuickBase with the installation information. 
  
19) Update SYSMON with the store information from the Goliath Tag Installation 
Report or verify that it has been updated by an FST, a DST or a DSM if they 
were on-site during the install.