Commissioning the RT   7–15
RT installation
Check the status of the installed SSIs as follows:
(Note that SSIs are not required for commissioning. They can be
installed after RT commissioning.)
1.
From the 
Status / CCM
 display, shown below,
Status                        
CCM
press the NEXT button to scroll to the SSI status menu:
Status                        
SSI 1
2.
Use the NEXT or PREV button to scroll to the SSI you
want to check:
Status                       
SSI 2
Note:
 SSIs are numbered SSI 1 through SSI 4, according to
their positions in the IDU chassis:
Chassis slot
SSI number
2
1
3
2
4
3
5
4
Slot 1 is occupied by the CCM.
3.
Press ENTER to show the status of the selected SSI:
SSI 2
OK
The possible status conditions for SSIs are:
OK
Degraded
Failed
Unknown
(as explained on page 7–14)
Check the status of each installed SSI.
Check SSI status