1027144– 0001  Revision D
Final steps   8–3
RT installation
After all equipment is installed and commissioned, visit each
installation area to inspect the equipment and make sure the area is
left clean and orderly.
Inspect all equipment to make sure:
All cables are dressed (as necessary) and not bent
excessively.
All connections are secure.
IFL connections are properly waterproofed.
IDUs, racks, and ODUs are properly grounded.
Antenna mount bolts are tightened.
ODU adjusters and the temporary installation collar have
been removed for future use.
Clean up all installation areas:
Make sure no tools or other objects are left on or near the
equipment.
Remove or neatly store any excess materials.
Remove all debris.
Before leaving the site, notify the appropriate customer
representative that the work has been completed. Ask the
representative to sign the work order, indicating that the
equipment has been installed and has passed the initial loopback
verification test(s).
The customer is responsible for connecting customer equipment to
the AIReach Broadband equipment through connections to
service–specific interface modules (SSI) modules. Refer to section
3.5 for information on the services and specific interfaces
provided by each SSI type.
8.2
Inspection, cleanup,
and sign–off
Inspection
Cleanup
Customer sign–off
8.3
Connecting
customer
equipment