Texas Instruments Bq24161EVM-721 Evaluation Module BQ24161EVM-721 BQ24161EVM-721 Datenbogen

Produktcode
BQ24161EVM-721
Seite von 21
Test Summary
2.2.4
Meters
Four equivalent voltage meters (VM #) and two equivalent current meters (CM #) are required. The current
meters must be able to measure 3-A current.
2.2.5
Computer
A computer with at least one USB port and a USB cable is required. The bq2416x evaluation software
must be properly installed.
2.2.6
HPA172 Communication Kit (USB TO GPIO)
A HPA172 USB-to-I
2
C communication kit is required.
2.2.7
Software
Download BQ2416xSW.zip from the charger's product folder, unzip the file, and double-click on the
SETUP.EXE file. Follow the installation steps.
Because the bq24160, bq24161, and bq24163 have the watchdog timers enabled, it is recommended that
you set the software's Reset Watchdog Timer to reset every 5 seconds. Otherwise, after 30 seconds of
operation, the IC enters Default mode. Note that the 27-minute safety timer is not reset by this function
and eventually times out if charging does not complete, unless the Safety Timer Time Limit is expanded
or disabled via the GUI. One way to reset the safety timer is to allow the 30-second watchdog timer to
expire. See Figure 3 in the data sheet for more information about the timers.
Also, it is generally helpful to activate the Write On Change functions, in the upper left of the GUI window,
to ON. The Write On Change function writes any changes to the GUI's check boxes, drop-down boxes,
and registers to the IC. Otherwise, the user must click the WRITE button to write changes to the software.
It is recommended that the user periodically click the READ button to find the IC's instantaneous status.
Alternatively, the AutoRead function can be activated to periodically update the GUI with the IC's status.
2.3
Recommended Test Equipment Setup
1. For all power connections, use short, twisted-pair wires of appropriate gauge wire for the amount of the
current.
2. Set Power Supply #1 (PS #1) for 6-V, 3-A current limit and then turn off supply.
3. If BAT_Load as shown in
is used, connect Power Supply #2 (PS #2) set to approximately 3.6
V to the input side (PS #2+/-) of BAT_Load, then turn off PS #2.
4. Connect the output side of the battery or BAT_Load in series with current meter (multimeter) #2 (CM
#2) to J2 and J6 or J3 (BAT, GND). Ensure that a voltage meter is connected across J2 or TP3 and J6
or TP9 (BAT, GND).
5. Connect VM #3 across J10 or TP7 and J14 or TP9 (SYS, GND).
6. Connect VM #4 across J15 or TP5 and J14 or TP9 (DRV, GND).
7. Connect J17 to HPA172 kit by the 10-pin ribbon cable. Connect the USB port of the HPA172 kit to the
USB port of the computer. The connections are shown in
.
7