Weil-McLain GOLD CGI 550-110-710/0107 Benutzerhandbuch

Seite von 68
Part Number 550-110-710/0107
33
GOLD CGi Gas-Fired Water Boiler — Boiler Manual
Fill the system with water
1.  Close manual and automatic
air vents
and boiler drain cock.
.
Fill to correct system pressure.
Correct pressure will vary with each
application. Typical cold water fill pressure for a residential system is
1 psi.
3.
Purge air
from system:
a.  Connect a hose to the purge valve (see
drain valves, item
6
, in
suggested piping diagrams on pages 3 through ,
Figure 18
through
Figure 23
). Route hose to an area where water can drain
and be seen.
b.  Close the boiler or system isolation valve between the purge valve
and fill connection to the system.
c.  Close zone isolation valves.
d.  Open quick-fill valve on cold water makeup line.
e.  Open purge valve.
f.  One zone at a time, open the isolation valves. Allow water to run
through the zone, pushing out the air. Run until no noticeable air
flow is present. Close the zone isolation valves and proceed with
the next zone. Follow this procedure until all zones are purged.
g.  Close the quick-fill water valve and purge valve and remove the
hose. Open all isolation valves. Watch that system pressure rises to
correct cold-fill pressure.
h.  After the system has operated for a while, eliminate any residual
air by using the manual air vents located throughout the system.
i.  If purge valves are not installed in system, open manual air vents
in system one at a time, beginning with lowest floor. Close vent
when water squirts out. Repeat with remaining vents.
4.  Open
automatic air vent
(diaphragm-type or bladder-type expansion
tank systems only) one turn.
5.  Open other vents:
a.  Starting on the lowest floor, open air vents one at a time until
water squirts out.
b.  Repeat with remaining vents.
6.  Refill to correct pressure.
Inspect system water piping
After filling the boiler and system with water,
inspect all 
piping
throughout the system for leaks. If found, repair
immediately. Repeat this inspection after the boiler has
been started and the system has heated up.
Leaks must be repaired at once.
Failure  to  do  so  can  damage  the
boiler, resulting in substantial prop-
erty damage.
Do  not  use
petroleum-based 
cleaning  or  sealing  compounds
in boiler system. Severe damage to
boiler will occur, resulting in sub-
stantial property damage.
Inspect base insulation
The  boiler  contains  ceramic  fiber
and  fiberglass  materials.  Use  care
when handling these materials per
instructions  on
page  68
 of  this
manual.  Failure  to  comply  could
result in severe personal injury.
Failure to replace
damaged insu-
lation or reposition insulation can
result in a fire hazard, causing severe
personal injury, death or substantial
property damage.
Check to make sure
base insulation is secure 
against
all four sides of the base. If insulation is damaged or
displaced,
do not
operate boiler. Replace or reposition
insulation.
Start-up — preparation 
(continued)
7a