2-6  Uncrating Your New Chiller 
! WARNING ! 
DUE TO THE SIZE AND WEIGHT OF SSC SERIES CHILLERS,  
STERLING RECOMMENDS USING BONDED PROFESSIONAL 
MILLWRIGHTS TO UNLOAD AND MOVE SSC SERIES
 
CHILLERS. 
 
Rig the chiller from the frame only, using spreader bars to prevent 
load transfer to any chiller components. Rig the frame from at least 
four points and balance the load before lifting to clear the skid. Use 
a forklift of adequate size when lifting the chiller by the fork 
pockets. 
 
Insert the forks all the way into the pockets and be sure to balance 
the load before lifting the chiller to clear the skid. Lift only as high 
as necessary. Use a pry bar to free the skid if necessary. Lower 
slowly. Retain the crating in case reshipment is necessary due to 
hidden shipping damage. 
 
Caution! 
Due to the weight of these units, use extreme caution 
when moving and placing SSC Series chillers.