þ  Check for proper pump rotation direction. To confirm proper 
rotation: 
1.  Observe a pump pressure gauge connected to the 
suction and discharge sides of the pump casing through 
two ¼” (approx. 6.4 mm) gauge cocks. 
2.  Close the gauge cock leading to the pump suction and 
open the gauge cock leading to the pump discharge. 
3.  Close the discharge butterfly valve, crack it open, then 
start the pump and observe the gauge.  
  If the gauge indicates within 15 psi (103.4 kPa/1.03 
bars) below the pump curve, pump rotation is 
correct. Pump rotation is clockwise opposite the 
shaft end
  If the gauge indicates 20 psi (137.9 kPa/1.38 bars) or 
more below the pump curve, the pump is running 
backwards. Reverse rotation by interchanging any 
two power mains to the pump motor or starter. 
  Recheck the pressure to be sure it increased. 
þ  Check the water level in the pump tank to be sure the pump 
does not run dry while the system piping is being filled. 
þ  Check your work and proceed to the Startup procedure in the 
following section. 
 
 
5-5  Remote Air-Cooled SSC Series Startup 
1.  Start the chiller by pushing the 
Start
 button on the control 
panel of the unit. 
2.  The touchscreen will display the Main Menu screen. 
3.  If your chiller has been setup to control the pump tank, the 
recirculation pump will turn on first, then after 5 seconds 
the process pump will turn on.  If configured with a standby 
pump, the lead/lag will control which pump turns on. 
4.  Fifteen (15) seconds after the last pump turns on the first 
compressor will turn on.  Based on the temperature of the 
water, the controller will turn on compressors every 15 
seconds. 
5.  Adjust the Freezestat cut-out, located in the main electrical 
enclosure, to 10°F (6ºC) below the process temperature set 
point you want.