Sterling Saw A0544325 Benutzerhandbuch

Seite von 38
 SMC Series Chillers
Page 13
2
Chiller Installation
2-1 Electrical Connections
Check serial tag voltage and amperage requirements and make sure your electrical service
conforms. See Figure 4 on Page 12 for total running amps.
Bring properly sized power leads and ground from a fused disconnect (installed by your
electrician) to the main power terminal in the chiller’s electrical enclosure.
;
  Electrical connections must comply with all applicable electrical codes.
;
  The chiller must be grounded in accordance with NEC Article 250.
;
  Voltage must be within 10% of the chiller’s nameplate rating.
2-2 Process Water Connections
;
  All external chilled water connections to the process must be of adequate size.
;
  See Figure 6 on Page 18 for sizing recommendations.
;
  The largest possible openings and passages should be provided for the flow of chilled water
through platens, dies, molds or other pieces of equipment.
Important!
Keep any pressure drop in external process piping
to an absolute minimum for optimum unit operation.
To Process
Connect the 
TO PROCESS
 chilled water supply outlet to the process being cooled.
From Process
Connect the 
FROM PROCESS
 chilled water return inlet to the return from the process back into
the chiller for cooling and recirculation.
;
  Sterlco recommends a strainer on the 
FROM PROCESS
 return line.