Startup Checklists
4-1 Introduction
Follow the check lists below for the startup of your new chiller. These lists assume the
installation information elsewhere in this manual has been read and followed. New chillers
should be started up and checked by a qualified refrigeration service technician.
4-2 SMC Pre-Startup Checklist
 
1.  Check the shipping papers against the serial tag to be sure chiller size, type and voltage is
correct for the process that will be controlled.
 
2.  Check the transformer primary voltage connections to be sure they are configured for the
electrical power you are using. The voltage at the main power connection must read
within +/-10% of the voltage listed on the serial tag. Electrical connections must conform
to all applicable codes.
 
3.  The chilled water 
TO PROCESS
 and 
FROM PROCESS
 connections should be completed.
 
4.  Be sure the reservoir tank and chilled water circuit piping are filled with water.
 
5.  The air-cooled condenser should have an adequate supply of air for proper operation.
 
6.  Connect main power to the chiller and run the chiller just long enough to see if the pump
is generating normal pressure.
 
7.  Check your work and proceed to the SMC Startup Checklist section below.
4-3 SMC Startup Checklist
 
1.  Turn 
ON
 the chiller. The SMC chiller should continue to run until the switch is turned
OFF
.
 
2.  Put the SMC chiller under a process load.
 
3.  Set the microprocessor control to the desired process temperature setpoint using the
, and 
 buttons. See Chapter 5 on Page 27 for more information.
 
4.  Check the pump amp draw and pump pressure. The amp draw reading must be within the
running load and service factor amps.
 
5.  Operate the chiller, looking for leaks and listening for unusual noises or vibrations that
could indicate improper operation.