SYSTEM CHECKOUT
IMPORTANT
Perform all Static Checkout Procedures for the 
applicable relay module shown in Table 8 before 
starting these procedures.
WARNING
Explosion Hazard.
Can cause serious injury or death.
Do not allow fuel to accumulate in the combustion 
chamber for longer than a few seconds without igniting 
to prevent danger of forming explosive mixture.
Close manual fuel shutoff valve(s) if flame is not 
burning at end of specified time.
WARNING
Electric Shock Hazard.
Can cause serious injury or death.
1. Use extreme care while testing system. Line voltage 
is present on most terminal connections when 
power is on.
2. Open master switch before removing or installing 
R7140 Relay Module.
Make sure all manual fuel shutoff valve(s) are closed before 
starting initial lightoff check and Pilot Turndown tests.
Do not put the system in service until you have satisfactorily 
completed all applicable tests in this section and any others 
recommended by the original equipment manufacturer.
Limit trial for pilot to ten seconds. Limit the attempt to light 
main burner to two seconds after fuel reaches burner nozzle. 
Do not exceed manufacturer nominal lightoff time.
CAUTION
Equipment Malfunction or Damage Hazard.
Incorrect wiring can cause equipment damage.
Each relay module type is unique. Using existing 
wiring on a relay module change can cause equipment 
damage.
IMPORTANT
1. If the system fails to perform properly, refer to the 
Troubleshooting section.
2. Repeat all required Checkout tests after all 
adjustments are made. All tests must be satisfied 
with the flame detector(s) in their final position.
Equipment Recommended
S7800A Keyboard Display Module 
Volt-ohmmeter (1M ohm/volt minimum sensitivity) with:
• 0-300 Vac capability.
• 0-6000 ohm capability.
• 0-10 Vdc capability.
Checkout Summary
Table 9 provides an overview of checkout steps performed for 
each applicable system.
See Installation Instructions for location of component parts 
and terminal locations.
Table 9. Checkout Steps and Applicable Detection Systems.
Preliminary Inspection
Perform the following inspections to avoid common problems. 
Make certain that:
1. Wiring connections are correct and all terminal screws 
are tight.
2. Flame detector(s) is clean, installed and positioned 
properly. Consult the applicable Instructions.
3. Combination of amplifier and flame detector(s) is 
correctly used. See the amplifier specifications.
4. Plug-in amplifier and purge card (if required) are 
securely in place.
5. Burner is completely installed and ready to fire; consult 
equipment manufacturer instructions. Fuel lines are 
purged of air.
6. Combustion chamber and flues are clear of fuel and fuel 
vapor.
Checkout Step
Piloted 
Systems DSI Systems
Infrared Flame 
Detectors
Flame Rod 
Systems
Ultraviolet 
Flame Detectors
Preliminary Inspection
X
X
X
X
X
Flame Signal Measurement
X
X
X
X
X
Initial Lightoff Check for Proved Pilot
X
Initial Lightoff Check for Direct Spark Ignition
X
Pilot Turndown Test
X
Ignition Interference Test
X
Hot Refractory Saturation Test
X
Hot Refractory Hold-in Test
X
X
X
X
X
Ignition Spark Pickup
X
Response to Other Ultraviolet Sources
X
Flame Signal with Hot Combustion Chamber
X
X
X
X
X
Safety Shutdown Tests
X
X
X
X
X