Ventilation Requirements 
 
 
 
Indoor Units
If compressors or condensing units are located in a machine 
room,  adequate  ventilation  air  must  be  provided  to  avoid 
an excessive temperature rise in the room. To allow for peak 
summer temperatures a 10°F temperature rise is recommended, 
although a 15°F rise might be acceptable.  
With compressors with remote condensers, approximately 10% 
of the heat rejected is given off by the compressor casting and 
the discharge tubing. The correct formula for calculating the 
ventilation requirement of the Indoor Parallel unit is:
 
 
 
CFM = 10% of THR / hr 
 
 
 
 
     10° TD
The air intake should be positioned so that air passes over the 
units. All State, Local, and National codes should be followed.
Electrical
To insure the proper operation of equipment and reduce the 
possibility of interruption of  refrigeration due to electrical  
power failure, the following precautions must be observed:
•   All electrical work must be done in accordance with the 
National Electrical Code and existing local codes
•   The power supply must be the same as specified on the unit 
data plate
•   An adequate power supply must be provided
•   Voltage fluctuations in excess of 10 percent must  
be corrected
•   Overload  relays  (Carrier  compressors  only)  are  selected 
in accordance with specified limits as determined by the 
motor-compressor manufacturer. They must not be changed 
in size or shorted-out
•   Control panels must be provided with a single phase, 60 
Hertz supply. See the unit wiring diagram for the voltage 
requirement
•   Before starting up a parallel unit, insure that all fuses and 
motor-protective devices are in place and that all wiring is 
secure. A complete wiring diagram for troubleshooting the 
unit will be found inside the control panel cover
Refrigerant Piping
The system as supplied by Heatcraft, was thoroughly cleaned 
and dehydrated at the factory. Foreign matter may enter the 
system by way of the field piping required.  Therefore, care must 
be used during installation of the piping to prevent introduction 
of foreign matter.
Install all refrigeration system components in accordance with 
all applicable local and national codes and in conformance 
with good practice required for the proper operation of the 
system.
Proper size refrigeration lines are essential to good refrigeration 
performance. Suction lines are more critical than liquid or 
discharge lines. Oversized suction lines may prevent proper oil 
return to the compressor. Undersized lines can rob refrigeration 
capacity and increase operating cost. Consult the line sizing 
charts in this manual for proper pipe sizes.
The following procedures should be followed:
1. Do not leave dehydrated compressors or filter-driers open 
to the atmosphere
2. Use only refrigeration grade copper tubing, properly sealed 
against contamination
3.  Suction  lines  should  slope  1/4”  per  10  feet  towards  the 
compressor
4. Discharge lines should slope 1/4” per 20 feet toward the 
condenser
Suction P-Traps
•   Provide P-Traps at the base of each suction riser of four (4) 
feet or more to enhance oil return to the compressor. Use a 
P-Trap for each 20 feet section of riser. See Figure 4 below:
*The P-Trap should be the same size as the horizontal line
See Figure 5 below
Parallel Compressor Systems
Figure 4. P-Trap Requirements
Figure 5. P-Trap Construction