NOTICE 
These installation procedures must be followed by qualified personnel or warranty will be void. 
Local codes regarding installation vary greatly from one area to another. The National Fire Protection Association, 
Inc. states in its NFPA 96 latest edition that local codes are the “authority having jurisdiction” when it comes to 
installation requirements for equipment. Therefore, installations should comply with all local codes. 
The installation must conform with local codes, or in the absence of local codes, with the National Fuel Gas Code, 
ANSI Z223.1, Natural Gas Installation Code, CAN/CGA-B149.1, or the Propane Installation Code CAN/CGA-
B149.2, as applicable, including: 
1. The appliance and its individual shutoff valve must be disconnected from the gas supply piping system during 
any pressure testing of that system at test pressures in excess of 1/2 psi (3.45 kPa). 
2. The appliance must be isolated from the gas supply piping system by closing its individual manual shutoff valve 
during any pressure testing of the gas supply piping system at test pressures equal to or less than 1/2 psi (3.45 
kPa). 
 
S
TEP 
1:
 
U
NPACKING
 
IMMEDIATELY INSPECT FOR SHIPPING DAMAGE 
All containers should be examined for damage before and during unloading. The freight carrier has assumed 
responsibility for its safe transit and delivery. If damaged equipment is received, either apparent or concealed, a 
claim must be made with the delivering carrier. 
Apparent damage or loss must be noted on the freight bill at the time of delivery. The freight bill must then be 
signed by the carrier representative (Driver). If the bill is not signed, the carrier may refuse the claim. The carrier 
can supply the necessary forms. 
A request for inspection must be made to the carrier within 15 days if there is concealed damage or loss that is not 
apparent until after the equipment is uncrated. The carrier should arrange an inspection. Be certain to hold all 
contents plus all packing material. 
 
1. Cut the banding straps and remove the corrugated cardboard surrounding the Sectional Fryer Filter System. Do 
not remove any of the attached tags or labels until the appliance is installed and working properly. 
2. Cut the banding strap holding the appliance to the wooden skid. 
3. If the appliance is to be installed on 6" legs, go to Step 2a. 
If the appliance is to be installed on 6" casters, go to Step 2b. 
If the appliance is to be installed on a caster frame, go to Step 3. 
S
TEP 
2
A
:
 
A
TTACH 
L
EGS
 
A set of four legs is packed with units ordered with legs. (For units ordered with casters, go to Step 2b.) 
A threaded leg pad is fastened to the base frame at each corner. Each leg has a corresponding mating thread. The 
legs can be adjusted to overcome a slightly uneven floor.  
1. Raise the appliance sufficiently to allow the legs to be attached. For safety, “shore up” and support the appliance 
with an adequate blocking arrangement strong enough to support the load. 
2. Screw the legs into the holes in the centers of the leg pads. 
3. Lower the appliance gently onto a level surface. Never drop or allow the appliance to fall. 
4. Go on to Installation Step 3.