Bil-Jax Personal Lift ESP 19 Benutzerhandbuch

Seite von 106
 
4 — MAINTENANCE 
3.  Once the battery voltage reaches a predetermined level programmed in the 
electronic control, the yellow “80% CHARGE” LED will illuminate. 
4.  The charge will be completed 3-1/2 hours after the yellow “80% CHARGE” 
LED is lit. The charger and all LED’s will automatically shut off. The battery 
charge level indicator should indicate at least 3/4 charge. 
NOTE: 
 If the battery voltage does not reach the 80% level within 14 hours, the 
charger will shut off and the “CHECK BATTERY” LED will light up. 
CAUTION
 
Before making or breaking connections between charger and battery, always 
remove the power cord from the 115 volt outlet. For more information, refer to 
the instructions supplied with the battery charger. 
5.  After the charge cycle is completed, disconnect the battery charger cord from 
the wall outlet, place it back into its box, and close and latch the lid. LIFT 
WILL NOT OPERATE IF THE LID IS NOT CLOSED SECURELY.
 
4-6  LIFT  CHAINS  AND  SLIDE  BLOCKS 
WARNING
 
Do not operate a unit on which any chain assembly is damaged or in need of re-
placement. Operating a unit with a damaged chain can cause severe injury or 
death to personnel and damage to equipment. 
Inspect all lift chains every 6 months. Inspect for signs of wear, split leaves, loose pins, 
clevis damage, and elongation. Replace any chain that is damaged in any way. Chain as-
semblies may be ordered from your dealer or direct from the factory. Do not operate a 
unit on which any chain assembly is damaged and in need of replacement. 
Chain Elongation Inspection 
Refer to Figure 4-11. Measure 20 pitches of chain. Twenty pitches of new chain should 
measure 12.5 in. (31.75 cm). Replace the chain if a 20-pitch length measures over 12.75 
in. (32.385 cm). 
  
Figure 4-11.   Chain Elongation Inspection 
 
4-13