Utica Boilers UB90-200 Installationsanweisungen

Seite von 2
CONDENSATION / EXHAUST KIT INSTRUCTIONS
Kit #550002946
Replacement kit for 90-200 BOILER
• Instructions are for replacing the exhaust tee and 
condensate trap assembly with drain exiting bottom of 
the exhaust tee on the 90-200 boiler allowing boiler to 
properly drain. 
• Particulate will collect in the drain plug on exhaust tee. 
Drain plug on exhaust tee can be removed for cleaning. 
• Follow instructions TO TURN OFF GAS TO APPLIANCE 
found on Operating Instructions label on boiler or in 
Installation, Operation & Maintenance Manual. Verify all 
electrical power to boiler is turned off.
Kit Installation:
 WARNING
Electrical shock hazard. Turn OFF electrical power supply at 
service panel.
!
  
1. 
Remove front jacket panel(s).
 WARNING
Burn hazard.  Verify heat exchanger has cooled or use 
appropriate personal protection equipment.
!
  
2. 
Cut exhaust pipe 5½" from tee flange. See figure 1. 
Before cutting vertical exhaust pipe, verify it is secured 
and will not fall. Cut existing exhaust pipe and edge. 
See Cut A.
3. 
Cut condensation line just below ½" tee. See Cut B.
4. 
At boiler exhaust outlet, loosen downstream pipe clamp 
on rubber coupling.
5. 
Remove assembly from rubber coupling.
6. 
Assemble parts 1 through 3.  Thread item 4 onto tee.  
Slide coupling onto existing exhaust pipe.  Insert other 
end into rubber coupling at boiler's exhaust outlet.
7. 
Assemble remaining kit parts. See Figure 2. Assemble 
drain piping then attach assembly to threaded fitting in 
exhaust tee. See item 4.
8. 
Cut existing condensate lines. Use new parts as guide 
for measuring where to cut remainder of existing 
condensation line pipes. See Cut C.
9. 
Connect existing line with new ½" condensate line 
coupling.
 P/N 240010634 Rev. A  [06/2014]
Kit installation shall be completed by qualified agency.
 WARNING
Fire, explosion, asphyxiation and electrical shock hazard.  
Improper installation could result in death or serious injury.  
Read this instruction and understand all requirements, 
including requirements of authority having jurisdiction, 
before beginning installation.  Installation not complete until 
appliance operation verified per Installation, Operation & 
Maintenance Manual provided with boiler.
!
  
Figure 1 - Exhaust Pipe and Condensation Line Cuts
CUT A
5-1/2”
CUT B
CUT C
10. 
Verify all joints are air-tight and cemented.
11. 
Verify hose clamp at exhaust outlet is tightened.
12. 
Resume operation using OPERATING INSTRUCTIONS 
found on Operating Instructions label on boiler or in 
Installation, Operation & Maintenance Manual.
13. 
Verify proper operation by following START UP 
PROCEDURE in Installation, Operation & Maintenance 
Manual.
14. 
Install front jacket panel(s).