B O I L E R   F E E D   S Y S T E M  
D A T E :   4 / 3 / 0 3  
R E P : 2 / 1 / 9 9  
 8
2.2 OPERATING INSTRUCTIONS 
CAUTION:
 
Check all electrical terminals and piping connections for tightness before start-up. 
2 . 2 . 1   F A M I L I A R I Z A T I O N   W I T H   M A N U A L ( S )
 
The user of the feed system and boiler system must familiarize himself with this manual to be sure 
he is prepared to operate and maintain the system properly. 
The operating instructions should be kept in a safe place and available to all who may be working 
or operating the feed system.   
READ THE MANUAL BEFORE ATTEMPTING A START-UP 
 
2 . 2 . 2   T U R N I N G   T H E   S Y S T E M   O N
 
Make sure all valves are open that need to be open to the feed system in order to operate the 
feed system.  The tank should fill up to half full with make-up water and the valves to the pumps 
on the suction end discharge side should also be opened and the strainers should be clean.  The 
pump should have been vented (if required) and all other instructions followed in this manual and 
also in the manufacturer’s data manuals for each particular item supplied.  When the tank has 
been filled to at least half full and all other instructions followed, the feed system is ready for 
operation.  Power may be turned on to the system for operation.  The boiler should also be 
checked to make sure it is ready to receive water and is working properly.  
2.3 MAINTENANCE SCHEDULE 
Post a maintenance schedule in accordance with the recommendations in this manual. A typical 
schedule is included in this manual.