II. Unpack Boiler
CAUTION
Do  not  drop  boiler.    Do  not  bump  boiler  jacket 
against floor.
A
.  REMOVE CRATE 
1.  Remove all fasteners at crate skid.
2.  Lift outside container and remove all other inside 
protective spacers and bracing. Remove vacuum 
relief valve and miscellaneous trim bag containing 
safety/relief valve, and pipe fittings.
B
.  REMOVAL OF BOILER FROM SKID
1.  Boiler is secured to base with 2 bolts, 1 at left front 
and 1 at right rear. Remove both bolts.
2.  Tilt boiler, "walk" boiler backward, and set rear 
legs down on floor.  Tilt boiler backward, pull skid 
forward and set front legs down on edge of skid.  
Install close nipple, tee, and plug in return coupling.  
See Section III and Figure 5.  Point tee toward 
permanent return location.
3.  Tilt boiler backward and remove skid. Be careful not 
to damage Burner or Jacket.
C. 
DETERMINE PROPER HINGE LOCATION FOR 
BURNER SWING DOOR.  Boiler is shipped with 
hinges on left side.  Approximately 12 inches are 
required on the hinge side for burner clearance.  If there 
will be less than 12 inches from left side of boiler to 
wall, move hinges to right side (refer to Paragraph D).
D
.  HINGE LOCATION CHANGE (if required) (refer to 
Figure 3).
1.  Pull 2 halves of Burner Swing Door Interlock apart. 
Swing Door Interlock is connected to T-T terminals 
on R7184P Control. Lift Honeywell R7184P Control 
off of Burner Junction Box and disconnect wiring 
harness from burner.  
2.  Remove 8 sheet metal screws from jacket.  Remove 
rear jacket box and bend both sides of Jacket 
Wrapper up, see Figure 22.
3.  Remove 2 (two) 5/16" - 18 x 3" long hex head cap 
screws and flat washers from right side of door. 
Remove 2 hairpin cotter pins and 2 hinge pins 
from hinges on left side of door and remove Door 
Assembly from boiler.  Inspect Front and Rear Door 
Insulation Pieces and Combustion Chamber Liner, 
see Paragraph G.
4.  Remove 4 hex nuts from bolts that attach hinges and 
hinge spacers to left side of Tubesheet. Remove 4 
hex head cap screws that attach hinges to door.
5.  Attach 2 hinge brackets & spacers to Tubesheet and 
2 hinge brackets to Door on right side of boiler.  3 
Holes in each Hinge Bracket must line up with 3 
matching holes in Spacer, Tubesheet or Door.  See 
Figure 3.  Tighten hex nuts, bolts and screws by 
hand only.
6.  Replace door assembly.  Hinge brackets attached to 
door must rest on top of hinge brackets attached to 
tubesheet.  See Figure 3.  Slide hinge pins through 
hinges from top and install cotter pins.  Close door 
and install 5/16" - 18 x 3" long hex head cap screws 
through flat washers and left side of door and into 
tapped holes in tubesheet.  Tighten all hex nuts, 
bolts and screws.  When door is installed properly, it 
is parallel to Tubesheet when viewed from top and 
sides.
7.  Bend sides of Jacket Wrapper down and attach 2 
Jacket Straps to 4 slots at bottom of Jacket Wrapper 
sides with sheet metal screws.  Install Rear Jacket 
Box with 4 sheet metal screws. See Figure 22.
8.  Connect wiring harness to burner Junction Box 
and install Honeywell R7184P Control, see Wiring 
Diagram, Figure 15 or 15A. 
  Reconnect Swing Door Interlock.
E
.  INSTALL BOILER CONTROL.
1.  Pull bulb and capillary tube out of hole in back of 
control.  Insert bulb in immersion well on top of 
boiler and secure control with set screw in control.
2.  Secure flexible conduit to Jacket Wrapper side with 
conduit clamp and sheet metal screw.  Conduit must 
be on same side of boiler as Swing Door hinges.
F
.  MOVE BOILER TO PERMANENT POSITION by 
sliding or walking.
G
.  INSPECT FRONT AND REAR DOOR INSULATION  
AND COMBUSTION CHAMBER LINER
1.  OPEN BURNER SWING DOOR on front of boiler. 
Use flashlight to inspect insulation secured to 
front and rear doors.  Inspect ceramic fiber blanket 
secured to bottom of combustion chamber.  Inspect 
inner and outer door gaskets.  Replace any damaged 
pieces.