3.4.2
Startup for systems that use flame-proof cable 
1.
Check to make certain that all field wiring power is turned OFF.
2.
Remove the end cap nearest the cable entries to gain access to the transmitter 
electronics.
3.
Install the cable and cable gland.
4.
Complete the field connection wiring.
5.
Connect a flow computer to the communications line on the Daniel3812 Liquid  
Ultrasonic Flow Meter.
6.
Apply electrical power to the system to ensure the field connections are working 
correctly. Allow the system to run for the time specified by the customer (usually one 
week) and an electrician has fully tested the connections. After the Acceptance Test is 
witnessed and approved, seal the conduit.
7.
Power down the system and apply the sealing compound to the conduit and allow to 
set in accordance with manufacturer specifications.
8.
Install the security latches and wire seals on the Transmitter Electronics Enclosure end 
caps (
9.
Install the wire seals on the Base Enclosure hex head bolts and on the Shroud covering 
the meter body (
10.
Install the security wire seals on the shrouds covering the transducers and cables. Refer 
to the section appropriate for your meter design:
11.
Connect electrical power to the system.
12.
Set or configure the meter using Daniel MeterLink. For additional installation 
information refer to the system wiring diagram (
), Daniel MeterLink 
Software for Gas and Liquid Ultrasonic Meters Quick Start Manual (P/N 3-9000-763) and 
use Daniel MeterLink Field Setup Wizard to complete the meter configuration.
HAZARDOUS VOLTAGE INSIDE
Do not open the Transmitter Electronics Enclosure when an explosive gas atmosphere is 
present. Disconnect equipment from supply circuit before opening.
 
Failure to remove power may result in serious injury or death.