Tone Detection Verification Test (#42)
This test verifies that the call-progress tone-detection and the tone-level measurement 
capabilities of the GPTD port are functioning properly.
Table 452: Test #42 Tone Detection Verification Test 
Error 
Code
Test 
Result
Description / Recommendation
ABRT
The system was not able to allocate every resource needed for this test, or 
there was an Internal system error.
1
ABRT
The system could not allocate every resource needed to test the 
call-progress tones.
1001
ABRT
The system was unable to put the GPTD port in the appropriate mode to 
test it.
1002
ABRT
The system could not allocate time slots for the test connection. This can 
happen when the system is heavily loaded. If the system is not heavily 
loaded, then test the TDM-BUS via test tdm 1 or test tdm 2.
1. Retry the command at 1-minute intervals up to 5 times.
1003
ABRT
The system could not allocate a Tone-Clock for the test connection. This 
may be caused by a heavy load on the system or by a faulted Tone-Clock.
1. Check to see if there are any alarms against the Tone-Clock in the port 
network where the test ABORTed. If so see the recommended 
procedures for 
2. If a new Tone-Clock has been inserted, allow about 1 minute for 
maintenance to run on the newly-inserted circuit pack.
3. Retry the command at 1-minute intervals up to 5 times.
2000
ABRT
Response to the test request was not received within the allowable time 
period.
1. Retry the command at 1-minute intervals up to 5 times.
2006
ABRT
The active Tone-Clock circuit pack or a Tone Detector circuit pack may not 
be functioning properly.
1. Test the active Tone-Clock circuit pack in the port network with test 
tone-clock location, and see 
2. Retry the command at 1-minute intervals up to 5 times.