Avaya 03-300430 User Manual

Page of 2574
Communication Manager Maintenance-Object Repair Procedures
1332 Maintenance Procedures for Avaya Communication Manager 3.0, Media Gateways and Servers
 
System Technician-Demanded Tests:
Descriptions and Error Codes
Investigate tests in the order presented. By clearing error codes associated with the Local 
Digital Looparound test (#58), you may also clear errors generated from other tests in the 
sequence.
NPE Crosstalk Test (#6)
The NPE Crosstalk Test verifies that this port’s NPE channel talks on the selected time slot and 
never crosses over to time slots reserved for other connections. If the NPE is not working 
correctly, 1-way and noisy connections may be observed. This test is part of a port’s long test 
sequence and takes about 20 to 30 seconds to complete.
Table 464: System Technician-Demanded Tests: DS1-BD 
Order of Investigation
Short Test 
Sequence
Long Test 
Sequence
D/ND
1
1. D = Destructive, ND = Nondestructive
NPE Crosstalk test (#6)
X
ND
Hybrid Electronic Power Feed test (#56)
X
ND
Hybrid Circuit and Conference Circuit test (#57)
X
ND
Local Digital Looparound test (#58)
X
ND
Remote Digital Looparound test (#59)
X
X
ND
Station Lamp Update test (#60)
X
X
ND
Station Audits test (#61)
X
X
ND
Ringer Update test (#62)
X
X
ND
Table 465: Test #6 NPE Crosstalk Test 
Error 
Code
Test 
Result
Description / Recommendation
ABRT
Could not allocate the necessary system resources to run this test.
1. Retry the command at 1-minute intervals up to 5 times.
 1 of 4