BRI XID Test (#628)
This test checks the D-channel connection between the server and an endpoint or adjunct.
In this test, a D-channel XID frame is sent to the endpoint or adjunct over the point-to-point 
signaling link.  The test passes if the endpoint or adjunct responds with a layer-2 
XID-RESPONSE frame
This test must be administered to not run in the Station Administration screen for ports on a 
TN2208.
Table 245: Test #628 BRI XID 
Error 
Code
Test 
Result
Description / Recommendation
1000
ABRT
The BRI-SET, ASAI-ADJ, ATT-ADJ, LGATE-AJ, ATTE-AJ is busy.  The test 
cannot be executed at this time:
1. Pause momentarily (30 seconds) and re-execute at this time.
2. If this problem persists, escalate this problem.
Note: A BRI-PORT can also be busy.  When using this for BRI-PORT/
ABRI-PORT tests, the words “BRI-SET, ASAI-ADJ, ATT-ADJ,” can be 
changed to “BRI-PORT, ABRI-PORT, ATT-ADJ.”
1005
ABRT
The endpoint is not administered to support XID testing.
1. If the endpoint documentation reflects support XID testing, use change 
station extension and change the XID Testing field on the screen 
to y.
1113
ABRT
The signaling link between the switch and the endpoint is down.
1. Use test port location long to clear any errors that prevent 
establishment of the signaling link.
2. Examine the results of the Signaling Link Status test (#626) that is run 
as part of this command.  If this test aborts or fails, follow the repair 
procedure for Test #626.
3. If the XID test (#628) continues to abort, escalate the problem.
1139
ABRT
The PN’s packet bus is out-of-service.
1. Follow the repair procedures for the packet bus.
2. After completing step 1, execute test port location long and 
review the results of the BRI Port Local LAN Loop Around test (#618) 
to verify the repair.