1.5 
Mounting Stand Installation 
1.  Construct a form for the mounting pad according to the specifications shown below. Be 
sure to level the top edge of the form and that the top of the form is a minimum of four (4) 
inches above ground level.  We suggest that you contact the local building department to 
determine the required depth of the pad since soil conditions and code requirements vary 
from city to city. 
2.  Set conduits, reinforcing bars and/or wire mesh if required. The number of conduits is 
determined by the application requirements. We suggest using a minimum of four (4) 
conduits.  1-High voltage power lines; 2-Low voltage control lines; 3-Loop lead-in wires 
(open loop); 4-Loop lead-in wires (reverse loops).  Conduits can be set in the areas 
indicated in the illustration.  See SECTION 2.  Set additional conduits as required for your 
application.  NOTE: If conduits are not set in the pad, they can be routed to a J box 
where connections to the operator can be made after it is installed. There are four (4) ½-
inch knockouts in the operator for this purpose. 
4
39.25
4
22.0
1.75
4
Minimum 4
inches above
ground level.
Pad depth determined
by soil conditions and
local building codes.
Minimum depth is 18
inches.