1)  Frame in the enclosure for the unit with framing material. The framed 
opening for the assembled kit is 42-1/2" high x 40-1/2" wide x 20-1/16" 
deep (1080mm  H x 1029mm W x 508mm D), see Diagram 1. Also 
see Diagram 2 for corner installations.
Note:   When constructing the framed opening, please ensure there 
is access to install the gas lines when the unit is installed. 
See diagram 3 for details.
2)  For exterior walls, insulate the enclosure to the same degree as the 
rest of the house, apply vapour barrier and drywall, as per local instal-
lation codes. (Do not insulate the fi replace itself.)
3)  The unit does not have to be completely enclosed in a chase. A non-
combustible header must be used. You must maintain clearances 
from the vent to combustible materials: See "Clearances" section.  
Combustible materials can be laid against the side and back standoffs 
and the stove base.
FRAMING & FINISHING
42-1/2"
(1080mm)
40-1/2”
(1029mm)
Min. 20-1/16"
(508mm)
Non-Combustible
Header
(On Edge)
Non-Combustible Studs
(when installing the full screen front only)
The  HeatWave Duct Kit has different 
clearance and framing requirements, 
check the HeatWave manual for details.
Diagram 2
Diagram 3
Note:    Height is from the base of the unit. Take into consideration 
the hearth height and material.
 
  Height = 42-1/2" plus height of hearth.
WARNING: When installing the Full Screen Doors
The Full Screen Front  requires additional non combustible facing and 
non-combustible framing.  Ensure the 10-1/4" above the fi replace, 6" 
on both sides and both the header and side studs are non-combustible 
materials. All other clearances, including mantel, remain the same.
WARNING: When installing the 
Full Screen Doors
The Full Screen Front  requires 
additional non combustible facing 
and non-combustible framing.  
Ensure the 10-1/4" above the 
fi replace, 6" on both sides and 
both the header and side studs 
are non-combustible materials. 
All other clearances, including 
mantel, remain the same.