AIR PRESSURE SWITCH OPERATION
The control system monitors the “state” of the air pressure switches individually through 
three separate circuits (see wiring on diagram page 39). The “state” of the switch refers to 
whether the switch contacts are open or closed. See the construction drawings on page 18.
Before each call for heat begins, 
before the blower starts, the control system performs a 
diagnostic test. During this test the control system checks the air pressure switches. The 
switches must be in their correct normal state at this point. 
The Blower Prover is a normally open switch and the Blocked Intake/Exhaust switches are 
normally closed. If the Blower Prover is not verified open or the Blocked Intake/Exhaust 
switches are not verified closed during this test; the control system would lock out and 
display a fault message indicating which pressure switch had caused the fault condition. IE: 
“Blower Prover Failure.”
After the blower starts
 the Blower Prover switch contacts must activate (close) for the 
water heater to continue in the Sequence of Operation (see page 40). If the Blower Prover 
switch contacts do not close after the blower starts, the control system would lock out and 
display a fault message; IE: 
“Blower Prover Open.”
The Blocked Intake and Blocked Exhaust switches must remain closed at all times. If the 
control system senses the contacts of either of these switches are open it will lock out and 
display a fault message; IE 
“Blocked Inlet” or “Blocked Exhaust Vent”
Normal State
Activated State
Blower Prover 
Air Pressure Switch
Normally open contacts,
close on a rise in pressure.
(contacts open - before blower starts)