Crown Boiler 24-03 User Manual

Page of 90
44
Figure 40b:  Water Boiler - Pressure Relief Valve 
Hook-Up
 
placement.  The 14 gauge mounting bracket must 
be attached to the jacket first using four (4) #8 x ¾” 
drill point sheet metal screws.
 
One may find it easier to install some of the conduit 
connectors with their corresponding conduit runs onto 
the RTC back panel before mounting to the bracket.  
The actual controller can and should be removed from 
the back panel during the mounting process.  This 
will eliminate the potential for accidental damage to 
the controller.  The RTC back panel is mounted onto 
the bracket with (4) #8-32 x ½” type F, Phillips Pan 
head screws supplied with the controller.  The middle 
3 rear knockouts should be used before utilizing the 5 
knockouts exiting the bottom of the control.  Depending 
on the final configuration, most of the controller 
connections could be used.  Typically, the return sensor, 
actuator control and boiler pump exit the rear of the 
controller.
 
Wire the RTC controller to the various components 
as shown below.  The “Mix” and “Outdoor” sensor 
are optional and must be connected if outdoor reset 
function is desired.  The outdoor reset function on 
this controller cannot be used in a multiple boiler 
application.  A boiler sequencer must be used when an 
outdoor reset feature is required in a multiple boiler 
application.