10.  Fit tubing provided into the proper place, as shown.  
Make sure that the discharge line ends up on the 
inside of the suction line. Cut ice machine suction 
line to fit new tubing.  Deburr suction line before 
fitting new tubing in. 
 
 
 
NOTE:  IF REPLACING COMPRESSOR INTO 
A REMOTE CONDENSER ICE MACHINE, 
MAKE SURE TO FIRST FOLLOW THE 
INSTRUCTIONS A, B, AND C BELOW 
BEFORE PROCEEDING TO INSTRUCTION 
#11. 
 
A.  Cut process tubing approximately 3” from the 
horizontal portion of the tube.  Make sure to cut 
both ends of the tube to make sure that a “T” 
fitting can be placed in between the pieces.  
 
 
 
 
B.  Place “T” fitting in between process tubing and 
place pieces of additional tubing between open 
end of T and HPR valve, as shown below. 
 
 
 
C.  Return to instruction #11. 
11.  Place armaflex insulation provided in kit on suction 
line, as shown in picture below. Slide insulation up 
tubing and secure while brazing. 
12.  Braze all tubing into place.  Purge system with 
nitrogen during all brazing operations on the ice 
machine. 
13.  Use electrical tape to seal suction line insulation. 
 
 
 
14.  Reattach the wiring harness to the compressor. 
 
 
 
15.  Replace the filter/dryer before evacuating the 
machine.  Make sure that filter/dryer tubing is not 
rubbing against the compressor. 
16.  Evacuate machine to 500 microns. 
17.  Charge the machine with nameplate charge. 
18.  Make sure that all tubing is not rubbing against 
anything else in the machine.   
19.  Reinstall corner post that was removed earlier and 
place electrical cover on compressor. 
20.  Reinstall back panels of ice machine. 
 
 
 
 
 
 
 
 
 
 
8006173 
Sheet 2 of 3 
06/25/01 
Horizontal 
Portion 
Approx. 3”