5.9. 
Operation at Wake Up from Power Shutdown 
The operation at wake up from the power shutdown is shown below. 
When PMUCTLR:IOCTMD bit is set, the I/O state is kept during the wake up sequence from the power 
shutdown. The maintenance of the I/O state continues until PMUCTLR:IOCT is set. 
When PMUCTLR:IOCTMD bit is cleared , the maintenance is effective during the wake up sequence. The 
register setting of the I/O port shall be effective after the wake-up completion. 
On waking up from power shutdown, there is a case that the maintenance of the I/O latch is not released. 
After waking up from power shutdown, PMUCTLR.IOCT bit must be written "1" for releasing the 
maintenance of I/O 
 
 