EMC QLA22xx User Manual

Page of 78
3
Configuring a CLARiiON Boot Device
3-15
Configuring an EMC Boot Device
9. Press 
ESC
 to exit the 
Fast!UTIL
 Options menu.
10. Reboot the host.
What Next?
The next step depends on the topology:
Preparing the Fabric
You can configure a switched fabric to support multiple hosts and 
multiple storage systems. For this setup, we will describe only the 
minimum configuration required for the boot LUN and server.
EMC recommends that you use switch zoning in all configurations to 
ensure consistency if your fabric grows. 
The configuration below requires an existing knowledge of zoning and 
switch fabric concepts. The procedure explains the necessary steps to enable 
boot functionality for the storage system. This configuration does not cover 
the impact of zoning changes to other devices that will use the same 
connections. You should confirm your overall topology requirements and 
configuration before implementing any zoning changes.
Other devices on the fabric may introduce load and demand on the interlink 
components and storage system that can affect boot LUN performance and 
correct functionality.
The switch fabric must be configured initially so that the boot HBA is 
visible only to a single port on the storage system. That is, there must 
be only one zone containing the boot HBA and one SP port until 
installation is complete, even if you will install failover software later. 
This can be accomplished in one of three ways (described following 
this list):
Switch fabric soft zoning (by WWPN)
Switch fabric hard zoning (by switch port)
Physical connection of only one SP port to the fabric