Schneider Electric E4800 User Manual

Page of 48
PowerLogic
TM 
EM4800 Series
 930-110-01-B.00
Installation 
04/2011
© 201
 Schneider Electric All Rights Reserved
20
Delta service metering
To use the PowerLogic EM4800 meter in a Delta service, the line-to-line 
voltage from the Delta service must be reduced to 120V line-to-line using 
appropriate potential transformers. Metering a Delta service requires only 
two potential transformers, and only two CTs for phase A and C. Using the 
phase B CT is optional.
For a three-phase Delta panel with the 120V variant of the meter:
Connect meter terminal A to the voltage disconnect phase A (red wire)
Connect meter terminal C to the voltage disconnect phase C (blue wire)
Connect meter neutral terminal to meter terminal B (black wire)
Connect earth wire to earth post using lug provided (see Figure 11)
Figure 11:  PowerLogic EM4800 meter three-phase Delta service 
connection 
8
4
5
6
9
2
1
3
7
Legend:
1     BX cable 
2     Earth
3     Phase C (blue)
4     Phase B (black)
5     Shorting jumper
6     Sense voltage terminal block (J3)
7     J3-B to J3-N shorting wire
8     Phase A (red)
9    0.75-inch (1.9-cm) strain relief