Installing the NetAXS-123 Panels
Installation
Installation
5. When the installation is complete, the closing screen appears:
6. Click
Finish
.
7. Connect the computer to the NetAXS-123 controller with a USB-A to Micro USB-B cable.
8. Turn on the power to the NetAXS-123 controller.
For login information, go to https://192.168.2.150.
3.7.2 RS-485 Communications
If a NetAXS-123 panel is to be placed onto a prexisting RS-485 dropline loop (NetAXS) it must be
setup as the Gateway panel. The interface allows the wiring of a Multidrop communication network of
up to 4,000 feet (1200 m) in length. Only one host converter device per dropline is supported.
setup as the Gateway panel. The interface allows the wiring of a Multidrop communication network of
up to 4,000 feet (1200 m) in length. Only one host converter device per dropline is supported.
Note:
NetAXS-123 must be the Gateway panel on an existing NetAXS loop. The NetAXS-123 panel
cannot be placed as a Downstream panel when the Gateway is a NetAXS system.
DIP switch position 6 on the NetAXS-123 panel selects whether the panel is a Gateway or
Downstream panel. The switch in the OFF position configures the panel as a Downstream panel; ON
configures a Gateway. The panel must be power cycled for a new switch setting to be recognized.
DIP switch position 6 on the NetAXS-123 panel selects whether the panel is a Gateway or
Downstream panel. The switch in the OFF position configures the panel as a Downstream panel; ON
configures a Gateway. The panel must be power cycled for a new switch setting to be recognized.
DIP
switch positions 1-5 are used to select the panel’s address on the network. Refer to
switch setting information.