DELL 350 User Manual

Page of 32
support.dell.com
Rack Installation Guide
1-7
Marking the Rack
1.
Determine where you want to place the bottom of the system.
CAUTION: If you are installing more than one system, install the first sys-
tem in the lowest available position in the rack. 
2.
Place the 1-U template over the front of the two-posts of the rack in the desired 
location.
3.
Position the bottom of the template in line with the desired bottom position of 
the system chassis.
4.
Mark the upper and lower-mounting positions on the vertical rails as shown by 
the V-notches on the sides of the template. 
Each 1-U (1.75-inch) vertical space has three holes, with center-to-center spacing 
between holes (beginning at the center of the top hole of a 1-U space) of 0.625, 
0.625, and 0.5 inch (see Figure 1-5). 
Figure 1-5.  Two-Post Open-Frame Relay Rack 1-U Hole Spacing
1.75 inches (1 U)
0.5 inch
0.625 inch
0.625 inch
0.5 inch
2D786bk0.book  Page 7  Thursday, January 18, 2001  8:44 PM