Installing the Dell UPS into the rack: 
Install the ReadyRails followed by the UPS chassis.  Finally install the battery modules into the UPS chassis & connect 
the DC leads.  Finish by installing the UPS front panel. 
Install the optional external battery module (EBM), Network Management Card (NMC), Environmental Monitoring 
Probe (EMP) and PDU(s)
2
, if ordered. 
Note:  The Dell UPS equipment is heavy.  Refer to the user guide for complete guidance on safety.  Some key points 
are: 
 
You should typically place the UPS at the bottom of the rack for a lower centre of gravity 
 
Extend the rack stabilization feed during installation to prevent the rack tipping 
 
Ensure you follow health & safety recommendations for working with heavy & electrical equipment 
 
 
                                                           
2
 Dell 16 Amp and 32 Amp PDUs can be plugged into Dell UPS. Dell 10kW UPS model with 2 x 32A outlets is tested with Dell 32 
Amp PDU types for fit. 