Installing the Dell UPS into the rack:
Install the ReadyRails followed by the UPS chassis. Finally install the battery modules into the UPS chassis & connect
the DC leads. Finish by installing the UPS front panel.
Install the ReadyRails followed by the UPS chassis. Finally install the battery modules into the UPS chassis & connect
the DC leads. Finish by installing the UPS front panel.
Install the optional external battery module (EBM), Network Management Card (NMC), Environmental Monitoring
Probe (EMP) and PDU(s)
Probe (EMP) and PDU(s)
2
, if ordered.
Note: The Dell UPS equipment is heavy. Refer to the user guide for complete guidance on safety. Some key points
are:
are:
You should typically place the UPS at the bottom of the rack for a lower centre of gravity
Extend the rack stabilization feed during installation to prevent the rack tipping
Ensure you follow health & safety recommendations for working with heavy & electrical equipment
2
Dell 16 Amp and 32 Amp PDUs can be plugged into Dell UPS. Dell 10kW UPS model with 2 x 32A outlets is tested with Dell 32
Amp PDU types for fit.
Actual carton may vary by model