15. To configure panels and breakers using the software configuration
tool, continue to the following section, Initial Panel and Breaker
Configuration (Using the Software Configuration Tool)."
To configure panels and breakers using the optional display,
continue to Step 16.
16. Click Disconnect to disconnect from the EMS−UGK. Verify that Not
Connected" displays at the bottom of the page.
17. Close the software configuration tool and remove the configuration
cable.
18. Activate the reset switch on the bottom of the electronics module:
hold the switch for 10 seconds or until the display (if installed) turns
off, then release the switch.
19. Continue to Initial Panel and Breaker Configuration (Using the
Initial Panel and Breaker Configuration (Using the
Software Configuration Tool)
To configure the panels and breakers:
1.
Click the Panel Config tab to display the EMS Panel Settings page.
2.
Verify that the Number of BCM Panels Installed is correct for your
installation.
If you change the value, click Save Panel Config to save the setting to
the EMS−UGK. Depending on communication speed, updates take
effect within 15–20 seconds.
3.
Select the panel number to configure (Panel Selected).