UPS INSTALLATION PLAN AND UNPACKING
EATON Powerware
®
 9395 UPS (1000–1100 kVA) Installation and Operation Manual  
S
  164201764 Rev 1 www.powerware.com
3−20
S
The REPO switch wiring must be in accordance with NEC Article 725 Class 2
requirements.
S
The maximum distance between the REPO and the UPS cannot exceed
150 meters (500 feet).
S
Alarm relay contacts have a maximum current rating of 5A and a switched voltage
rating of 30 Vac and 28 Vdc.
S
Alarm relay wiring should be a minimum of 22 AWG.
3.2.4
Distributed Bypass Power Wiring Preparation
Read and understand the following notes while planning and performing the
installation:
S
All distributed bypass UPS rectifier inputs must come from one source and all
bypass input feeds must come from one source.
S
Distributed bypass UPS input wiring size requirements and output wiring size
requirements from the UPSs to the tie cabinet or distribution panel are the same as
listed in Table 3-4, Table 3-5, Table 3-6, or Table 3-7 starting on page 3−9.
S
If the load requires a neutral, a bypass source neutral must be provided. If the load
does not require a neutral and there is no neutral conductor connected at the
bypass input, a neutral to ground bonding jumper must be installed. Install neutral
conductors from the UPSs to the common point of connection (tie cabinet), and
then install a system neutral to ground bonding jumper. The bonding jumper must
be copper wire. DO NOT install both a source neutral and a bonding jumper.
If the recommended system neutral bonding jumper installation method cannot be
accomplished, each UPS should have a separate neutral to ground bonding jumper
installed. See Table 3-4, Table 3-5, Table 3-6, or Table 3-7 starting on page 3−9 for
UPS neutral bonding jumper wire sizes. The bonding jumper must be copper wire.
DO NOT install both a source neutral and a bonding jumper.
S
The UPS cannot be installed in a high−resistance ground application.
S