UPS Installation Plan and Unpacking
Use the following basic sequence of steps to install the UPS:
1.
2.
3.
4.
5.
6.
7.
Have authorized service personnel perform preliminary operational checks and
start up the system.
NOTE  Startup and operational checks must be performed by an authorized Eaton Customer Service
Engineer, or the warranty terms specified on page W−1 become void. This service is offered as part of the
sales contract for the UPS. Contact an Eaton service representative in advance (usually a two−week notice is
required) to reserve a preferred startup date.
3.1
Creating an Installation Plan
3.2
Preparing the Site
For the UPS system to operate at peak efficiency, the installation site should meet
the environmental parameters outlined in this manual. If the UPS is to be operated at
an altitude higher than 1500m (5000 ft), contact an Eaton service representative for
important information about high altitude operation. The operating environment must
meet the weight, clearance, and environmental requirements specified.
3.2.1
Environmental and Installation Considerations
The UPS system installation must meet the following guidelines:
S
The system must be installed on a level floor suitable for computer or electronic
equipment.
S
The system must be installed in a temperature and humidity controlled indoor area
free of conductive contaminants.
Failure to follow guidelines may void your warranty.
For Field Installed UPM (FI−UPM) weights and dimensions, refer to the Powerware
9395 Field Installed UPM Mechanical Installation Manual, listed in paragraph 1.8 on
page 1−7.
Figure 3Table 3